Approximately 300 hectares of Finnish forest — roughly 500 football fields — were reportedly cleared for a Google data-centre project before its environmental-impact assessment was concluded. Finland's supervisory agency LVV is investigating whether Tuike Finland Oy failed to complete a legally required EIA prior to converting over 200 hectares of land. Google says forestry operations complied with the Forestry Act and that ecological surveys protected high-value areas, while conservationists say satellite imagery shows designated nature sites were bulldozed. The case raises broader questions about how rapidly expanding AI infrastructure should be regulated and could influence future European oversight of large data-centre developments.
Google Accused of Clearing Roughly 300 Hectares of Finnish Forest for Data-Centre Expansion — Regulatory Probe Underway

About 300 hectares of forest in Finland — an area often compared to roughly 500 football fields — were cleared for a planned Google data-centre expansion before a formal environmental-impact assessment (EIA) was completed, according to reporting. The clearing reportedly occurred while the broader environmental review process was still ongoing.
Investigation and Legal Issues
Finland's supervisory agency LVV is investigating whether Tuike Finland Oy, the local project company acting for Google, failed to carry out a legally required EIA before making permanent changes to more than 200 hectares of land. Officials emphasize that this is a regulatory inquiry, not a legal verdict: no final ruling has been issued.
Project Scale
The local clearing is part of a much larger investment commitment. Google has announced at least €13 billion of planned spending on Finnish AI and data-centre infrastructure through 2028, with facilities in Hamina, Kajaani, Muhos and Vaala. The company describes the programme as its largest single investment in Europe.
Responses From Google and Conservationists
Google told AFP that "tree felling activities have been taking place in compliance with Forestry Act requirements," adding that ecological surveys were performed before work began and areas of high environmental value were protected during forestry operations.
"In our view, operations at this construction site should be suspended until it is clarified whether the project is in compliance with the law,"
— Hanna Halmeenpää, chair of the Finnish Association for Nature Conservation, rejects Google's framing. She says satellite imagery shows four areas designated as nature sites in the local plan were bulldozed, which could fragment wildlife corridors and disturb local bird populations. The association has asked LVV to halt activity at the site, but available coverage has not reported any suspension.
Wider Implications
The core dispute centers on sequencing and oversight: AI infrastructure and hyperscale data-centre projects require substantial physical land, concrete and timber, and when construction or clearing moves faster than environmental review processes the ecological costs can materialize before approvals are finalized. LVV must now determine whether compliance with Finland's Forestry Act is sufficient when a separate, broader EIA remained incomplete at the time tree-felling began. The outcome could set an important precedent for how European regulators oversee large-scale data-centre development going forward.
Next steps: LVV's inquiry is ongoing; authorities will decide whether additional enforcement or remediation is required once the investigation concludes.